Join us Sundays: Worship // 9:45 AM | Sunday School // 11 AM Wednesdays: Worship // 6 PM

Go

Building Expansion

Update - July 6, 2017

0

THE WALLS ARE UP AND THE FLOOR IS BEING POURED: The walls were all completed about two weeks ago, the steel support and roof decking are in place and the floors are being poured with completion on July 12, 2017. Progress is much more visible as enclosure begins to take place. Continue to pray...

Continue reading…

Update - June 7, 2017

0

REACH: The third year of our REACH Campaign starts this month, so all the Central family is asked to continue their giving and pledges. If you give on an annual basis, please consider when you will fulfill your 2017 gifts. Our current total is $4.3 M which has slowed some in the past few months...

Continue reading…

Update - May 10, 2017

0

REACH AND GIVING: At the end of this month of May, we will have reached the end of our second year of pledges and giving for the Children’s Building. The third year of our giving program will begin on June 1, 2017. To date, we have received $4.232 M on our way to the $13.7 M cost of the...

Continue reading…

Update - April 3, 2017

0

INTRODUCING THE BRICK PAVER PROGRAM: Central has now launched the exciting Brick Paver Program to provide an opportunity for church members and families to become a permanent part and legacy of the Children’s Building. It will be a lasting way to honor and memorialize family members and...

Continue reading…

Update - January 30, 2017

0

UPDATE ON BUILDING EXPANSION January 30, 2017 A $4.0 MILLON PRAISE: God has through you, the Central family, provided over $4.0 M in just over a year and half of our REACH Campaign to fund the new Children’s Building on our way to pay for the $13.7 M project. Take time today to thank and...

Continue reading…

Update - January 20, 2017

0

CONSTRUCTION: Construction is progressing at a slower than expected pace and the completion date is being discussed with Dudley Construction to see what we can do to stay close to the projected completion date of late October or early November. Weather days are always included in project...

Continue reading…

Update - December 2, 2016

0

CONSTRUCTION: Construction of the building foundation is moving forward at a great pace and should allow for walls to start being put in place in early 2017. Some of the driveways have been completed and other parts of the new parking lot are progressing. We are still on schedule and hope to...

Continue reading…

Update - September 20, 2016

0

NOW AT $3 MILLION AND COUNTING: As of today, God has provided through the Central family $3,162,208 in giving to the Children’s Building on our way to the needed $13.7 Million. We completed the first year of giving two months ago and now enter into the second year. If you have never...

Continue reading…

Update - August 20, 2016

0

CONSTRUCTION STARTED: Site preparation for construction on the new Children’s Building and new parking lot has started. The process of preparing the site of the new parking lot and tearing out the existing parking lot where the new building will be located will take several weeks and is...

Continue reading…

Update - July 1, 2016

0

CONSTRUCTION TO START: Construction on the new Children’s Building is now projected to start on Monday, July 11, after finalizing the plans and working through the bidding process. Some equipment is now being moved onto the site with demolition of the parking lot to be the first phase, so...

Continue reading…

Previous12345